IAA Transportation is a major international event for logistics, commercial vehicles and the transport sector. At the 2026 event in Hanover, Milence demonstrated how battery energy storage can enable megawatt-level electric truck charging where grid capacity is limited.
The solution combined a Pixii PowerBase XLP battery energy storage system and Pixii Energy Architect energy management system (EMS), integrated with an Alpitronic HYC1000 charger. During testing, the solution delivered more than 1 MW of charging power while connected to a grid supply rated at only 260 kW.
The system demonstrated at IAA was not built as a temporary showcase. Following the event, the PowerBase XLP will become part of Milence’s charging hub in Osnabrück, Germany, supporting the rollout of high-power charging infrastructure for electric trucks.

| Customer | Milence |
| Locations | Arnhem, Netherlands; Hanover and Osnabrück, Germany |
| Industry | Electric truck charging infrastructure |
| Application | Battery-buffered megawatt charging |
| Pixii products | PowerBase XLP and Pixii Energy Architect (EMS) |
| Charging hardware | Alpitronic HYC1000 |
| Functions in use | Power boost |
| Usage | Enable megawatt charging despite limited grid capacity |
| Value proposition | Deliver high-power electric truck charging without relying on an equally large grid connection |
| Available grid connection | 260 kW |
| Recorded grid import | 173.9 kW |
| Recorded battery contribution | 855.8 kW |
| Recorded charger demand | 1,029.7 kW |
| Battery energy storage system | Pixii PowerBase XLP |
| Energy management | Pixii Energy Architect (EMS) |
| Charger | Alpitronic HYC1000 |
The electrification of heavy-duty transport is creating demand for much higher charging power. Electric trucks must take on large amounts of energy during limited charging windows, making megawatt-level charging increasingly important for long-haul transport and commercial fleets.
However, grid connections at charging sites may provide significantly less power than the chargers require. Reinforcing the grid can be costly and time-consuming, and sufficient capacity may not be available where charging infrastructure is needed.
Battery energy storage can bridge this gap by storing energy and releasing it when charging demand exceeds the power available from the grid.
For IAA Transportation in Hanover, Milence wanted to demonstrate electric truck charging at up to 1 MW.
The available grid connection was rated at only 260 kW – less than one quarter of the required charging power. The system therefore needed to supply the remaining power from battery energy storage while ensuring that grid import stayed within the available limit.
The solution also needed intelligent controls to coordinate the grid, battery energy storage system and charger in real time. Ramp-down control and no-export functionality were required to ensure controlled operation under the site’s grid constraints.
Pixii supplied a PowerBase XLP battery energy storage system controlled by Pixii Energy Architect EMS, the company’s energy management system.
The PowerBase XLP acts as a local energy buffer. Energy can be stored within the limits of the grid connection and then discharged when an electric truck requires more charging power than the grid alone can provide.

The Pixii Energy Architect continuously coordinates power flows between the grid connection, battery system and Alpitronic HYC1000 charger. During high-power charging, the EMS controls how much power is imported from the grid and how much is supplied by the battery.
The complete solution was integrated and tested at Milence’s facilities in Arnhem before being transported to Hanover and demonstrated at IAA Transportation.

Pixii PowerBase XLP is a large-scale battery energy storage system designed for power- and energy-demanding applications such as electric truck charging.
The system is fully integrated, pre-wired and factory configured on a steel skid with a container-format footprint. Its single-lift design allows it to be transported and deployed as one complete system, reducing installation time and on-site work.
During a recorded charging event, the Alpitronic HYC1000 charger drew 1,029.7 kW.
Only 173.9 kW was imported from the grid. The Pixii PowerBase XLP supplied the additional 855.8 kW from battery storage.
This enabled the charger to deliver more than 1 MW – over four times the rated capacity of the available grid connection.
Pixii Energy Architect EMS dynamically controlled the power flows between the grid, battery system and charger. Testing also verified controlled ramp-down and no-export operation. Ramp-down control ensures that charging power can be reduced in a controlled manner when required, while the no-export function prevents energy from being fed back into the grid.
Adding a battery energy storage system (BESS) to a charging facility can enable megawatt-scale charging even when the grid connection alone cannot provide the required power. The battery stores energy and supplements power from the grid during periods of high charging demand. This can make better use of existing grid capacity and reduce dependence on immediate grid reinforcement.
The pre-wired, factory-configured, single-lift design simplifies transport and on-site deployment, making PowerBase XLP suitable for projects where rapid deployment or later relocation may be required.
At IAA Transportation in Hanover, Milence demonstrated more than 1 MW of electric truck charging while drawing less than 260 kW from the grid. The demonstration gave fleet operators, charging operators and transport-industry stakeholders a practical example of how battery energy storage can overcome a constrained grid connection.
Following the event, the PowerBase XLP will be relocated to Milence’s charging hub in Osnabrück, Germany, where it will move into continued operational use supporting high-power charging for electric trucks.
A battery energy storage system supplies the additional power that the grid connection cannot provide. The grid and battery operate together, coordinated by an energy management system, to meet the charger’s power demand without exceeding the site’s grid limit.
During the recorded charging event, the Pixii PowerBase XLP supplied 855.8 kW. The grid supplied 173.9 kW, allowing the charger to draw a total of 1,029.7 kW.
The solution combined a Pixii PowerBase XLP battery energy storage system, Pixii Energy Architect energy management system and an Alpitronic HYC1000 charger.
Battery-buffered charging uses locally stored energy to supplement the electricity grid during high-power charging events. This makes it possible to deliver more charging power than the grid connection alone can support.
Battery storage can help charging operators deploy high-power infrastructure in grid-constrained locations, reduce peak grid demand and reduce dependence on immediate grid reinforcement.
Following the demonstration in Hanover, the PowerBase XLP will become part of Milence’s charging hub in Osnabrück, Germany. There, it will support the deployment of high-power charging infrastructure for electric trucks.